The Las Pailas II Geothermal Project is in an intense testing phase to integrate into the National Electric System (SEN) and generate sustainable electricity before the end of the first half of 2019. By the end of November, its construction progress exceeded 93%.
The plant, located in Liberia, will have 55 megawatts of installed capacity, firm and renewable, which will serve to ensure the base of the electricity demand curve.
From the Global Geothermal News archives:
- Wednesday, April 25, 2018 - Costa Rica: Construction of Las Pailas II Geothermal Project is Currently at 80%
- Monday, January 22, 2018 - Costa Rica: Drilling Completed for 55 MW Las Pailas II Geothermal Project
- Monday, September 18, 2017 - Costa Rica: Award for Geothermal Energy Pioneer Alfredo Mainieri Protti
- Friday, February 3, 2017 - Costa Rica: Construction of Las Pailas II Geothermal Project is Currently at 54%
- Monday, October 17, 2016 - Costa Rica: Mitsubishi Hitachi to Provide Turbine for 55 MW Pailas II Geothermal Power Project