(Courtesy Polaris Infrastructure) |
Vancouver, Canada-based Polaris Infrastructure Inc. has provided the following update with respect to the 2017/2018 San Jacinto drilling program.
- Successfully flow-tested new production well, SJ 12-4
- Successfully concluded drilling and initial flow-testing of new production well, SJ 12-5
- Planned above-ground infrastructure investments
- Assessment of options to stimulate SJ 4-2 are ongoing
"We are very pleased with the preliminary findings related to our two most recent geothermal wells at the San Jacinto project," said Marc Murnaghan, Chief Executive Officer of Polaris Infrastructure. "Although the new wells have not yet achieved stabilization, we are confident that they will result in a substantial increase in average generation."
From the Global Geothermal News archives:
- Tuesday, November 7, 2017 - Nicaragua: Third Well at San Jacinto Geothermal Project to be Drilled Soon
- Friday, June 16, 2017 - Nicaragua: New Injection Well Completed at San Jacinto Geothermal Project
- Tuesday, March 7, 2017 - Nicaragua: Turbine Maintenance Successfully Completed at the San Jacinto Geothermal Project