(Courtesy ZIZ Broadcasting Corporation) |
Equipment for the first phase of the geothermal development project on Nevis, began arriving on the island following shipping delays due to the recent passage of Hurricanes Irma and Maria, pushing the start-up dates from October to mid-November.
Installation and assembly are expected to commence in a day or two. The drilling process will follow and the exploratory drilling is estimated to take about 45 days.
DOSECC Exploration Services LLC, drilling contractors based in Salt Lake City, Utah, have been contracted by NREI to undertake the drilling process. The test well is projected to be 4,000 meters deep. It will be used to collect all data possible to satisfy the financiers.
On completion of the exploration, the data will be analysed and final adjustments will be made to the engineering. The production process is planned in early 2018.