Isaac Angel, CEO of Ormat spoke at the GRC Annual Meeting |
"The project expects to reach commercial operation by the end of 2017. We also initiated development of efforts in two projects in Nevada: Tungsten Mountain and Dixie Meadows are each expected to generate 25 megawatts to 35 megawatts, once they come online in 2017 or 2018. We have drilled several exploration wells both sides. And while drilling activities ongoing, we are making progress towards securing PPAs. We believe that these projects may qualify for the production tax credit."
"In Sarulla, Indonesia, engineering and procurement for the first phase is completed, while in progress for the other two phases. The construction for the first phase is in progress. The infrastructure work has been substantially completed. The major equipment including Ormat’s OECs and Toshiba’s steam turbine for the first phase have arrived to the country, larger portion already at the site. The drilling of production injection wells is also in-progress for all three phases, but currently the project company is experiencing some delays mainly in the meeting some of the drilling milestones as well as few EPC milestones."
"It should also be noted that project is facing some cost overruns resulting mainly from drilling. The consortium members are examining the significance of these cost overruns and their potential implications for the project’s budgets as well as for the financing of the project since the cost overruns and drillings delays may impact the project’s ability to drove on the debt financing and force additional equity investment by the consortium members."
Read More........