Entire 280 MW project to be commissioned by year end
The 140 MW is from two units – one of which has already completed reliability test while the other is expected to complete the test by mid August.
At the same time, two more units are expected to commence reliability tests in September and October respectively.
It is expected that before the end of the year, the entire 280 MW will be fully commissioned.