Yokogawa Electric Corporation announces that its subsidiary, P.T. Yokogawa Indonesia, has received an order from PT. PLN, a government-owned utility in Indonesia, to supply the control system for a project that will renovate the first of four 20 MWe power generation units at the Lahendong geothermal power plant, which is located in the Lahendong district on Sulawesi Island.

As part of this renovation project, the system used to monitor and control the steam turbine auxiliary facilities in unit No. 1 will be replaced with the CENTUM®VP integrated production control system. Yokogawa Indonesia will be responsible for engineering, installing, and commissioning the new system. This project is scheduled to be completed by February 2014, whereupon unit No. 1 will be returned to service.