Recent Achievements:
- Generated fleet wide total 65,303 MWh in the second quarter of 2013
- Delivered quarterly average availabilities of: Raft River - 89.3%, San Emidio - 91.5%, Neal Hot Springs - 72.2%
- Continued with final commissioning completion activities at Neal Hot Springs including 15-20 day outages at each plant to make final corrections, and received the certificate of final completion from the EPC contractor on June 27, 2013.
- Held 6 and 10 day planned outages at San Emidio and Raft River respectively to make normal repairs, upgrade equipment, and conduct warranty modifications.
- Completed drilling resource confirmation well at El Ceibillo project in Guatemala, and began well testing.
- Prepared for start of drilling at San Emidio 2 plant expansion.