Ram Power Announces Updates for the San Jacinto-Tizate Project (MarketWatch - press release)
Ram Power, Corp. has announced the following update for the San Jacinto Phase II expansion project in Nicaragua.
As required by the Phase II loan agreements, the company conducted a 30-day performance test on the Phase II unit to verify that the plant meets its minimum generation capacity. The Phase II expansion produced a total of 25,676 MWh versus the required 23,688 MWh in order to achieve certification. During the performance test, the plant maintained 99.94% availability, operating at the required 36 MW net output from the Phase II Fuji turbine and exceeding the requirements of the performance test.