Australia:

Completion of First Open Flow Test at Habanero 4 (News Release)

Geodynamics Limited has announced that the first open flow test for Habanero 4 has now been conducted. The staged open flow test achieved the planned maximum production rate of 35kg/s at a flowing pressure of 29 MPa (4,200 psi) through a variable choke, before the test was completed. The surface pressures indicate the well has additional capacity to flow at higher rates which were not attempted during this test. Temperature at 4,130 m cable depth was recorded at 241°C with a surface temperature of 191°C, and increasing, after 82 minutes of flow.