Thursday, December 10, 2015

Mexico: Construction Contract for 25 MW Los Azufres III, Phase II Project Awarded

CFE adjudica central geotérmica Los Azufres - CFE awards Los Azufres geothermal power contract (azteca noticias)

The Mexican Comision Federal de Electricidad (CFE) has awarded the 25 MW Los Azufres III, Phase II project to Spanish company TSK Electronica y Electricidad SA. It will have an average annual generation of 186.15 gigawatt-hours per year.

The project includes engineering, civil engineering, assembly and supply of main equipment and materials for the comprehensive construction of a geothermal power plant in Michoacan, whose estimated execution time is 30 months. TSK Electronica y Electricidad will use Fuji turbines.

The 50 MW Los Azufres III, Phase I was inaugurated in September.

Read More.......