Thursday, February 20, 2014

Philippines:

Tongonan Geothermal Power Plant is Back Online (BusinessWorld Online Edition)

The 112.5 MWe Tongonan geothermal power plant in Leyte is now fully restored following the return to service of the remaining unit of the plant that was damaged by typhoon Yolanda/Haiyan on Nov. 8 last year, EDC said in a disclosure yesterday.
"Further to our December 19 disclosure covering the Tongonan Plant’s return to service, i.e., “…beginning with first unit today [December 19], followed by the last two units up to the first quarter of 2014…”, we inform the Exchange that we have now energized the last remaining unit of our Tongonan Power Plant. All units, however, remain subject to close monitoring and/or additional tests."
Read More.....