Webpages

Tuesday, July 3, 2018

Nicaragua: New Wells at San Jacinto Geothermal Project Results in Increase in Generation.

Polaris Infrastructure Provides Operations Update (News Release)

(Courtesy Polaris Infrastructure)
Toronto-based Polaris Infrastructure Inc.  has provided an update with respect to operations at the San Jacinto geothermal plant and comment with respect to record-level power generation achieved during the second quarter of 2018.

"We are very pleased to report that the San Jacinto project, operated by the Company's wholly-owned subsidiary, Polaris Energy Nicaragua S.A., achieved record-level power generation in the second quarter of 2018 of 139,000 MWh (net). This equates to average delivered power generation of approximately 63.5 MW (net).  It is important to note that this includes the effect of planned downtime to commission the new HPS3 separation station during the month of April."