US Geothermal Inc : Mechanical Completion of 1st Power Module at Neal Hot Springs (News Release - 4-Traders)


Webcam photo of Neal Hot Springs 85% complete
(Courtesy U.S. geothermal)
U.S. Geothermal Inc., today announced that its construction contractor has provided a notice of mechanical completion for the first of three 7.3 net megawatt, air cooled power plant modules at the Company's Neal Hot Springs project, located in Malheur County, Oregon. The total project is about 90 percent complete with some 65% of the U.S. Dept of Energy project loan already drawn down to fund construction.